072 786 5027           info@ecopanel.co.za           5 Bloemfontein Road,  Edenvale
BUILD BETTER. LIVE BETTER          

Comparisons & Applications

Information through statistics

Comparison Chart Brick and Mortar

ECOPANEL HOLLOW BLOCKS AAC BLOCKS
Compressive Strength - Wall Section (N/mm²)
4.0 - 5.0
1.3 - 3.5
3.0 - 4.0
Direct Pullout (N)
Up to 2200
Up to 710
Up to 320
Density (Kg/m³)
600 ± 7%
1400 - 1900
400 - 1000
U Value (W/m².K)
Up to 0.274
2.3 - 2.8
0.3 - 0.4
Fire Rating (Insulation & Integrity)
3 Hours
Varies
0-4 Hours
Acoustic STC Rating (dB)
Up to 60
Up to 46
Up to 39
Joint Capacity (kN/m)
Up to 17.38
2 - 2.5
2 - 2.5
Flexural Strength-Face (kN/m)
Up to 8.10
N/A
N/A
Flexural Strength-Side
Up to 8.10
N/A
N/A
Axial Load Capacity (kN)
Up to 140.3
N/A
N/A
Plaster Requirement
Not Required
Required
Required
Wet Areas
Acceptable
Acceptable
Acceptable

Comparison Time

A comparison of time taken to build a finished wall (2 sides plaster) ready to paint on both side

ECOPANEL 2400 x 600 x 90 PANELS BLOCK AND MORTAR 200 x 400 x140
Step
Time
Step
Time
Location marking
0.5 hr
Location marking
0.5 hr
Bottom and top track cutting and setting
1.0 hr
Mortar mixing and setting out
1.0 hr
Install first panel with dowel bars
1.0 hr
Block laying
24 hrs
Installation of vertical panels
2 hrs
Curing time
24 hrs
Measuring and cutting of horizontal panels
1.0 hr
Manual plastering
5.0 hrs
Installation of horizontal panels
1.5 hrs
Curing time
48 hrs
Closing of head track
1.0 hr
Note: Block work walls cannot be built
higher than 6 courses without the mortar
setting i.e. 24 hours.

Rigid scaffolding is required to be fixed
for block work at 1.5m height.
Closing of joints
2.0 hrs
Finishing of joints
3.5 hrs
Note: Panels only require mobile scaffolding
and not restricted by height.
Total time
13.5 Hrs
Content
102.5 hrs

Comparison Cost

Brick/block and
mortar construction
Lightweight EcoPanel
wall construction
Cost per sq. metre of dwelling <80m²
R7071.00*
R5500.00
Cost per m² of walling incl. plaster
R530.00
R428.00

(No plaster needed)
Cost of raft foundation per m²
(typical)
R1020.00
R890.00

(uses 20% less steel)
Labour cost @R50/hr
(see table above for 16 m² area)
R1525,00

(based on 30,5 hours of labour time)
R675.00

(based on 13,5 hours of labour time)

*Based on March 2021 study by STATSSA (EstimationQS.com 2021)